General Information:

  • City / Area of Town:         City of Birmingham
  • Project Manager:             Douglass Stockham            244-4186
  • Pipeline Contractor:        BWWB
  • Project Cost (Est.):          $45,500.00 (Paving Work ONLY)
  • Project Duration:             25 Calendar Days (Paving Work ONLY)
  • Start Date (Est.):               5/2/17
  • Completion Date (Est.):  5/26/17 (or earlier)
  • Other Contact:                  Janice Acoff 244-4265

 

Customer Correspondence

 

NOTE: Each of these documents can be opened by the customer by clicking the link.

 

Project Roadways:

     Mains & Services to be Replaced

  • 25th Street SW between Pearson Avenue SW & Beulah Avenue SW
  • Beulah Avenue SW between 25th Street SW & 26th Street SW

 

 

Vicinity Maps: