General Information:
- City / Area of Town: City of Fairfield
- Project Manager: Douglass Stockham 244-4186
- Pipeline Contractor: REV Construction, Inc.
- Project Cost (Est.): $1,315,400.00
- Project Duration: 160 Calendar Days
- Start Date (Est.): 6/7/17
- Completion Date (Est.): 11/22/17 (or earlier)
- Other Contact: Janice Acoff 244-4265
Customer Correspondence
- Courtesy Letter (Project Area)
- Thermal Expansion (Project Area)
- Thermal Expansion Literature
- Thermal Expansion Illustration
- Project Summary Handout
- Project Roadways
NOTE: Each of these documents can be opened by the customer by clicking the link.
Project Roadways:
Mains & Services to be Replaced
- 60th Street Fairfield (FF) between Terrace Avenue FF & Court “F” FF
- 63rd Street FF between Terrace Avenue FF & Court “F” FF
- 63rd Street FF between Terrace Avenue FF & Dead-End of Roadway
- Avenue “D” FF between 59th Street FF & 60th Street FF