General Information:

  • City / Area of Town:         City of Birmingham / City of Tarrant
  • Project Manager:             Douglass Stockham            244-4186
  • Pipeline Contractor:         REV Construction, Inc.
  • Project Cost (Est.):           $1,541,1300.00
  • Project Duration:              150 Calendar Days
  • Start Date (Est.):               11/30/17
  • Completion Date (Est.):    4/30/18 (or earlier)
  • Other Contact:                  Janice Acoff 244-4265

 

Customer Correspondence

 

NOTE: Each of these documents can be opened by the customer by clicking the link.

 

Project Roadways:

    Mains & Services to be Replaced:

  • Fulton Avenue between 42nd Place North & Mississippi Street
  • 49th Court North between 41st Street North & 49th Terrace North
  • Pine Tree Lane between 87th Place South & Red Oak Road
  • 1st Avenue South between 85th Street South & 87th Street South
  • 86th Street South between 2nd Avenue South & Approximately 175’ NW of 3rd Avenue South
  • 86th Place South between 2nd Avenue South & Approximately 150’ NW of 3rd Avenue South
  • 86th Place South between 4th Avenue South & 86th Street South
  • 87th Street South between 4th Avenue South & 6th Avenue South

 

Vicinity Maps: