General Information:

  • City / Area of Town:          City of Fairfield
  • Project Manager:              Douglass Stockham            244-4186
  • Pipeline Contractor:         Global Construction & Engineering, Inc.
  • Project Cost (Est.):           $1,355,796.50
  • Project Duration:              100 Calendar Days
  • Start Date (Est.):              12/19/17
  • Completion Date (Est.):   4/6/18 (or earlier)
  • Other Contact:                  Janice Acoff 244-4265

 

Customer Correspondence

 

NOTE: Each of these documents can be opened by the customer by clicking the link.

 

Project Roadways:

          Mains & Services to be Replaced

  • Acadia Terrace FF between E.J. Oliver Boulevard & Court “B” FF
  • Terrace Avenue FF between Valley Road & 59th Street FF
  • 56th Street FF between E.J. Oliver Boulevard & Terrace Avenue FF
  • 57th Street FF between E.J. Oliver Boulevard & Terrace Avenue FF
  • 58th Street FF between Terrace Avenue FF & Dead-End of Roadway

 

 