General Information:

  • City / Area of Town:         Unincorporated Jefferson County
  • Project Manager:             Douglass Stockham            244-4186
  • Pipeline Contractor:         Rast Construction, Inc.
  • Project Cost (Est.):           $298,000.00
  • Project Duration:              70 Calendar Days
  • Start Date (Est.):               12/18/17
  • Completion Date (Est.):   3/2/18 (or earlier)
  • Other Contact:                  Janice Acoff 244-4265

 

Customer Correspondence

 

NOTE: Each of these documents can be opened by the customer by clicking the link.

 

Project Roadways:

     Mains & Services to be Replaced:

  • Woodhaven Road between Morgan Road & 70’ east of Russet Meadows Drive
  • Russet Woods Trail between Woodhaven Road & 30’ northward
  • Woodhaven Trace between Woodhaven Road & 40’ northward
  • Russet Meadows Drive between Woodhaven Road & 80’ southward

 

 

Vicinity Maps: