General Information:

  • City / Area of Town:        City of Birmingham
  • Project Manager:             Jay Trimm            244-4260
  • Pipeline Contractor:        Jones Utility & Contracting Company, Inc.
  • Project Cost (Est.):          $897,980.30
  • Project Duration:             120 Calendar Days
  • Start Date (Est.):               2/25/16
  • Completion Date (Est.): 6/23/16 (or earlier)
  • Other Contact:                  Janice Acoff 244-4265

 

Customer Correspondence

 

NOTE: Each of these documents can be opened by the customer by clicking the link.

 

Project Roadways:

Mains & Services to be Replaced

  • 9th Avenue North between 11th Street North & Approximately 60’ Southwest of 12th Street North
  • 10th Avenue North between 11th Place North & 13th Place North
  • 11th Place North between 10th Avenue North & Alice Street North / 10th Court North
  • 12th Street North between 10th Avenue North & Alice Street North / 10th Court North
  • 13th Street North between 10th Avenue North & Alice Street North / 10th Court North
  • 13th Street North between 10th Avenue North & Approximately 50’ Northwest of 9th Avenue North
  • 13th Place North between 10th Avenue North & Approximately 200’ Southeast of 10th Avenue North

 

Vicinity Maps: