General Information:

  • City / Area of Town:        City of Birmingham
  • Project Manager:             Douglass Stockham            244-4186
  • Pipeline Contractor:        Jones Utility & Contracting Company, Inc.
  • Project Cost (Est.):           $1,197,156.00
  • Project Duration:             145 Calendar Days
  • Start Date (Est.):              8/28/17
  • Completion Date (Est.):   2/20/18 (or earlier)
  • Other Contact:                 Janice Acoff 244-4265

 

Customer Correspondence

 

NOTE: Each of these documents can be opened by the customer by clicking the link.

 

Project Roadways:

Mains & Services to be Replaced

  • 1st Place South between 16th Avenue South & 17th Avenue South
  • 2nd Street South between 16th Avenue South & 17th Avenue South
  • Delta Street South between 8th Avenue South & 16th Avenue South
  • Gamma Street South between 8th Avenue South & 16th Avenue South
  • Beta Street South between 8th Avenue South & Dead-End of Roadway
  • 16th Avenue South between Delta Street South & Gamma Street South
  • 19th Street SW between Mayfield Avenue SW & Grant Avenue SW
  • 19th Street SW between Grant Avenue SW & Dead-End of Roadway
  • Mayfield Avenue SW between 18th Street SW & 19th Place SW
  • 20th Place SW between Mayfield Avenue SW & Dead-End of Roadway
  • 22nd Street SW between Mayfield Avenue SW & Dead-End of Roadway
  • 23rd Street SW between Mayfield Avenue SW & Dead-End of Roadway

 

 