Avenue "E" Ensley Phase One 

General Information:

  • City/Area of Town: City of Birmingham (Ensley)  
  • Project Cost: $80,000.00
  • Project Duration: 30 Calendar Days
  • Start Date (Est.): 1/6/14
  • Completion Date (Est.): 2/4/14

 
Project Roadways

 
Mains Killed & Services Relocated to Larger Mains:

  • Avenue “E” Ensley between 9th Street Ensley & approximately 150’ southwest of 10th Street Ensley
  • 10th Street Ensley between Avenue “E” Ensley & Avenue “F” Ensley

 
Vicinity Maps:

 

Click here to download map ►

 

Click here to download map ►


 

 

 