General Information:

  • City / Area of Town:        City of Birmingham
  • Project Manager:             Douglass Stockham            244-4186
  • Pipeline Contractor:        BWWB
  • Project Cost (Est.):          $211,200.00
  • Project Duration:             50 Calendar Days
  • Start Date (Est.):               4/4/16
  • Completion Date (Est.): 5/24/16 (or earlier)
  • Other Contact:                  Janice Acoff 244-4265

 

Customer Correspondence

 

NOTE: Each of these documents can be opened by the customer by clicking the link.

 

Project Roadways:

Mains & Services to be Replaced

  • 30th Avenue North between 16th Street North & 18th Street North
  • 16th Street North between 30th Avenue North & Approximately 60’ north of 30th Avenue North
  • 16th Street North between 30th Avenue North & ApproxMains & Services to be Replaced
  • 30th Avenue North between 16th Street North & 18th Street North
  • 16th Street North between 30th Avenue North & Approximately 60’ north of 30th Avenue North
  • 16th Street North between 30th Avenue North & Approx

 

Vicinity Maps: